• No1 : Chillers Manufacturer & Supplier in India
  • info@ozoneairsolution.com
Plot No.C1-539, GIDC Odhav,
Near Post Office, Road No.41,

Odhav, Ahmedabad-382415

(+91) 97276 21234

Troll Free Number

Commissioning Checklist for New Chiller Installation - Ozone | Air Solution

Commissioning is the most critical phase of any chiller project. A poorly commissioned unit will underperform, consume excess energy, and fail prematurely. Field experience shows that most early-life failures trace back to commissioning errors rather than manufacturing defects.

This chiller commissioning checklist is designed for plant engineers and facility managers overseeing a new chiller installation. Use this sequence to ensure operational reliability from day one.

1. Pre-Installation & Mechanical Checks

Foundation & Piping Readiness

  • โœ”
    Structural Leveling: Confirm the slab is level within ยฑ3 mm over the full footprint.
  • โœ”
    Pipe Support: Ensure evaporator and condenser nozzles are not bearing the weight of connected pipework.
  • โœ”
    Vibration Isolation: Verify shipping brackets are removed and spring isolators are properly adjusted.
  • โœ”
    System Flushing: Mandatory flushing of all water circuits to remove construction debris before connecting the chiller.

2. Electrical & Safety Interlocks

Voltage & Phase: Measure phase-to-phase voltage balance (imbalance < 2%) and confirm rotation matches the manufacturer's specification.

Flow Switch Testing: Simulate a flow failure on both chilled and condenser water loops. The chiller must trip and latch to prevent evaporator freeze-up.

BMS Integration: Verify BACnet/Modbus communication, addressing, and baud rate settings for remote monitoring.

3. Refrigerant Circuit & Vacuum

This stage is frequently rushed, leading to acid formation and bearing failure. Never skip the 500-micron rule.

Process Requirement
Leak Test 24-hour nitrogen pressure hold; adjust for ambient temp changes.
Vacuum Level Pull below 500 microns (0.5 mbar) using a calibrated electronic gauge.
Standing Test Isolate pump; vacuum must not rise above 1,000 microns in 30 mins.
Charging Charge by weight to nameplate specification; record all cylinder serials.

4. First Start-Up & Performance Verification

Once stable (15โ€“20 mins), record the following baseline parameters for the O&M manual:

  • Delta-T: Chilled water return vs. supply (target 5โ€“6ยฐC).
  • Suction/Discharge: Compare real-time pressures against design curves.
  • Superheat/Subcooling: Target 5โ€“10 K superheat to ensure no liquid slugging.
  • Actual COP: Calculate kW cooling output รท kW electrical input.

Common Mistakes to Avoid

1. Starting without flushing: Weld slag and debris will destroy evaporator plates in hours.

2. Jumpering safety switches: Bypassing a flow switch to “get it running” is the #1 cause of catastrophic freeze damage.

3. Skipping operator training: A chiller the team doesn’t understand is a chiller that will be misoperated.

Did You Like This Post? Share it :

Inquiry form


    This will close in 0 seconds

    Hiring Form


      This will close in 0 seconds